After 60 years was opened a new coal pit ¨Begići–Bištrani¨ at the brown coalmine RMU ¨Kakanj¨
In the pitmine „Haljinići“ of Brown Coal Mine ¨Kakanj¨, after more than half a century was opened new coal pit „Begići-Bištrani“, as replacement capacity for the current exploitation field .
The opening of the new pit is hystorical event not only for public utility Elektroprivreda BiH but also for Bosnia ansd Herzegovina are the words of dr. Elvedin Grabovica, General manager of JP EPBiH.
¨ For the pit opening EPBiH has invested 2,7 million KM. That will be followed by new procurement of dampers , bulldozers , widely fr. mechanism , machines for pits spaces and other equipment for the mines what will satisfy all international standards and provide new necessary conditions for begining of the exploatation .
For these procurements we are going to invest 45 million KM „ said dr.Grabovica and added that the coal from pit „Begići Bištrani“ are intended for the existing and for the future Block 8 at TPP „ Kakanj“ .