Location of the facility - the Bosna River, area of the City of Zenica
Type of facility – run-of-river power plant
Installed capacity - 16 MW
Annual generation - 77.26 GWh
Investment
Investment - BAM 126 million
Financing - Loans and funds of EPBIH
Project status
- Feasibility Study, Fichtner (Germany), Electroforce (BiH) and ERM (Germany), December 2012
- Concession Agreement – 2014
- Preliminary Design, Energoinvest Sarajevo, December 2015
Designer: Energoinvest d.d. Sarajevo
Auditor: Zavod za vodoprivredu d.d. Sarajevo - Biological Baseline Study and Environmental Impact Assessment Study; Consortium Oikon Zagreb, Geonatura Zagreb and HEIS Institut za hidrotehniku d.d. Sarajevo, January 2016
- Completed construction of phase 1: Connection of the local road to the main road M17 - in accordance with the Agreement with JP Ceste Federacija BiH d.o.o. and the Decision on Construction Permit, number UP1-03-19-2-992/23 dated February 6, 2024. year
Designer: Design&QC d.o.o. Sarajevo
Auditor: PRONASA d.o.o. Sarajevo
Contractor: Dobojputevi d.d. Doboj Jug
Supervision: PPG - Company for design and construction d.o.o. Sarajevo - Resolving proprietary and legal issue