Project Location – Konjic
Planned installed capacity – 90 MW
Annual production expected approximately - 230 GWh
Investment
Investment – 135 million euros
Financing – loans from KfW and EIB, KfW grant funds, and funds from EPBiH
Project status
Completed activities:
- Environmental permit obtained, i.e. a Decision has been issued confirming that an Environmental Impact Assessment is not required
Activities in progress:
- Preparation of documentation for obtaining the Urban Planning Permit