Thermal Power Plant „Tuzla“: 250 million KM for ecologic projects in period 1996-2017
Electricity in amount of 3.472.267 MWh was generated at Thermopower plant TPP "Tuzla¨ in 2017,and 115.665 MWh heating energy and technologic steam by spending 3,8 million tonnes of coal. Total investing of this power plant in the past year was 8,6 million KM without capital envestment so that 2,1 million KM was for ecologic project what presents 24 % of the total investment in the past year.
09. January 2018.
Adopted business plan of JP Elektroprivreda BiH d.d.- Sarajevo for 2018 – 2020
The forthy– eight (extraordinary) Assembly of Elektroprivreda BiH d.d.- Sarajevo, held on December 2018 in Sarajevo, adopted Business plan of public company JP Elektroprivreda BiH d.d. – Sarajevo for period 2018 - 2020
27. November 2017.
Loan Agreement on construction the Unit 7 was signed
At the Summit Initiative 16+1 in Budapest , on November 27th, 2017 , was signed a Loan agreement for financing the project of construction Unit 7- 450 MW at thermal power plant „Tuzla“
21. November 2017.
General manager was handed over awards for the achieved revenue, investments and Company's leading position on the market in field of electricity generation
Mirsad Jašarspahić, President of the Federation BiH Economic Chamber and Alena Ahmetspahić-Fočo, director of project Business magazine handed over awards to Bajazit Jašarević General manager of JP Elektroprivreda BiH for the achieved successful results in 2016, achieved revenue of EPBiH investments cash flow and Company's leading position on the market in field of electricity generation
10. November 2017.
Federation BiH Government – compliance for selection of project partner for Unit 7 construction
FBiH Government has accepted final information for selection the project partner for construction of Unit 7 - 450 MW at thermal power plant „Tuzla“; JP Elektroprivreda BiH d.d.-Sarajevo gave consent for selection of China Gezhouba Group Company Ltd - CGGC ( leader of Consortium )and China Energy Engineering Group, Guangdong Electric Power Design Institute Co., Ltd - GEDI ( member of the Cosortium ) for partner for project construction
10. November 2017.
US Ambassador visited JP Elektroprivreda BiH
Her excellency Maureen Cormack, the US Ambassador for Bosnia and Herzegovina, Peter Duffy USAID Mission Director to Bosnia and Herzegovina, Mak Kamenica Deputy Chief of Party of the USAID Enterprise Energy Efficiency and Edhem Brankovic as the representative of the Economic/Commercial office at the U.S. Embassy Sarajevo visited JP Elektroprivreda BiH d.d.-Sarajevo
03. November 2017.
Electricity generation increased at EP BiH's thermal power plants
In period January-October 2017. JP Elektroprivreda BiH generated 5.768 GWh of electricity
03. November 2017.
Record coal production in recent 20 years
In October 2017 was produced 509.770 tons of coal, which is the greatest monthly coal production since 2009. (since Concern was established )
18. September 2017.
The mines of the Concern EPBiH realize the highest production of coal
In August 2017 in the coal mines of Concern EPBiH was produced 478.374,92 tons of coal or 91,53% of Plan , in spite of unfavourable weather conditions and extremly high temperatures . This is the highest production ,with those from 2012 ,which was achieved in period from establishing Concern in 2009
07. September 2017.
In the mine pit Raspotočje released into trial work wide mechanised complex
On Thursday , September 7, 2017 on Day of company JP Elektroprivreda BiH, in mine pit Raspotočje ( brown coal mine Zenica ) released into trial work the wide mechanised complex with transport system machine for making cave rooms and transport